<> "The repository administrator has not yet configured an RDF license."^^ . <> . . . "Pengaruh getaran tanah (ground vibration) terhadap tingkat kestabilan lereng tambang PIT North Main Ridge di PT. J Resources Bolaang Mongondow"^^ . "PT. J Resources Bolaang Mongondow is an open pit gold mine. One of the\r\nactivities to get ore is to carry out blasting activites. One of the effects of blasting\r\nis ground vibration, this vibration at a certain level can causes disturbances to the\r\nstability of the slope. The further analysis is needed to determine the value of the\r\ndynamic Safety Factor (SF) which is affected by vibrations due to blasting.\r\nPit Main Ridge is the area that has the most frequent blasting activities,\r\ntherefore blasting needs to be controlled in order to the dynamic safety factor is not\r\nless than 1,1 in accordance with the Minister of Energy and Mineral Resources\r\nDecree No. 1827 K 30 MEM 2018. This research aimed to know the value of\r\ndynamic Safety Factor (SF) in section A-A’ and section B-B’ slope of Pit North\r\nMain Ridge.\r\nThe calculation results show that the longer the detonation distance, the\r\nsmaller the vibration value. The calculation of the Safety Factor (SF) of slope in\r\nthis study used the limit equilibrium method (General Limit Equilibrium) using\r\nRocscience Slide 6.0 software. In the slope stability analysis, the data processed\r\nare data of physical and mechanical properties of the slope, and the actual slope\r\ngeometry with pseudostatic analysis. Based on the slope simulation results with\r\nseismic coefficient is 0,024 g, section A-A’ slope has static Safety Factor (SF) value\r\nis 1,296 and dynamic is 1,233 and section B-B’ has static Safety Factor (SF) is\r\n1,534 and dynamic is 1,464 = PT. J Resources Bolaang Mongondow merupakan tambang emas dengan\r\nmetode open pit. Salah satu aktivitas untuk mendapatkan ore adalah dengan\r\nmelakukan kegiatan peledakan. Dampak peledakan salah satunya adalah getaran\r\ntanah (ground vibration), getaran ini pada tingkat tertentu dapat menyebabkan\r\ngangguan pada kestabilan lereng. Sehingga diperlukan analisis lebih lanjut untuk\r\nmengetahui nilai Faktor Keamanan (FK) dinamis yang dipengaruhi oleh getaran\r\nakibat peledakan.\r\nPit Main Ridge merupakan area yang memiliki kegiatan peledakan yang\r\nperlu dikontrol agar Faktor Keamanan (FK) dinamis tidak kurang dari 1,1 sesuai\r\ndengan Keptusan Menteri ESDM Nomor 1827 K 30 MEM 2018. Tujuan dari\r\npenelitian ini adalah untuk mengetahui Faktor Keamanan (FK) dinamis pada lereng\r\nsection A-A’ dan section B-B’ di Pit Main Ridge Utara.\r\nHasil perhitungan menujukkan bahwa semakin jauh jarak peledakan maka\r\nnilai getaran akan semakin kecil. Perhitungan nilai Faktor Keamanan (FK) lereng\r\npada penelitian ini menggunakan metode kesetimbangan batas (General Limit\r\nEquilibrium) dengan bantuan perangkat lunak Rocscience Slide 6.0. Pada analisis\r\nkestabilan lereng, data yang diolah merupakan data sifat fisik dan mekanik batuan\r\npenyusun lereng dan geomteri lereng aktual dengan analisis pseudostatik.\r\nBerdasarkan hasil simulasi lereng dengan koefisien seismik sebesar 0,024g, lereng\r\npada section A-A’ memiliki nilai Faktor Keamanan (FK) statis 1,296 dan dinamis\r\n1,233, section B-B’ memiliki nilai Faktor Keamanan (FK) statis 1,534 dan dinamis\r\n1,464 dengan koefisien seismik sebesar 0,024g."^^ . "2023-07-21" . . . . . . . . . . . "Institut Teknologi Nasional Yogyakarta"^^ . . . "Fakultas Teknik dan Perencanaan : Teknik Pertambangan, Institut Teknologi Nasional Yogyakarta"^^ . . . . . . . . . . . "Erry"^^ . "Sumarjono"^^ . "Erry Sumarjono"^^ . . "JESCLIANATA DEWINTA"^^ . "LOMBAN"^^ . "JESCLIANATA DEWINTA LOMBAN"^^ . . "Supandi"^^ . "."^^ . "Supandi ."^^ . . . . . . "Pengaruh getaran tanah (ground vibration) terhadap tingkat kestabilan lereng tambang PIT North Main Ridge di PT. J Resources Bolaang Mongondow (Text)"^^ . . . "lengkap Draft Skripsi_Jesclianata Dewinta Lomban_7100190099 (2)-1-16.pdf"^^ . . . "Pengaruh getaran tanah (ground vibration) terhadap tingkat kestabilan lereng tambang PIT North Main Ridge di PT. J Resources Bolaang Mongondow (Text)"^^ . . . "Pengaruh getaran tanah (ground vibration) terhadap tingkat kestabilan lereng tambang PIT North Main Ridge di PT. J Resources Bolaang Mongondow (Text)"^^ . . . "Pengaruh getaran tanah (ground vibration) terhadap tingkat kestabilan lereng tambang PIT North Main Ridge di PT. J Resources Bolaang Mongondow (Text)"^^ . . . "Pengaruh getaran tanah (ground vibration) terhadap tingkat kestabilan lereng tambang PIT North Main Ridge di PT. J Resources Bolaang Mongondow (Text)"^^ . . . "Pengaruh getaran tanah (ground vibration) terhadap tingkat kestabilan lereng tambang PIT North Main Ridge di PT. J Resources Bolaang Mongondow (Text)"^^ . . . "Pengaruh getaran tanah (ground vibration) terhadap tingkat kestabilan lereng tambang PIT North Main Ridge di PT. J Resources Bolaang Mongondow (Text)"^^ . . . "Pengaruh getaran tanah (ground vibration) terhadap tingkat kestabilan lereng tambang PIT North Main Ridge di PT. J Resources Bolaang Mongondow (Text)"^^ . . . "lengkap Draft Skripsi_Jesclianata Dewinta Lomban_7100190099 (2)-88-89.pdf"^^ . . . "Pengaruh getaran tanah (ground vibration) terhadap tingkat kestabilan lereng tambang PIT North Main Ridge di PT. J Resources Bolaang Mongondow (Text)"^^ . . "HTML Summary of #5560 \n\nPengaruh getaran tanah (ground vibration) terhadap tingkat kestabilan lereng tambang PIT North Main Ridge di PT. J Resources Bolaang Mongondow\n\n" . "text/html" . . . "TN Mining engineering. Metallurgy"@en . .